신발산업의 생산계획 시스템 정 영 준 In
this study we consider the problem of planning system for Footwear industry.
Due to the environmental change in market, delivery satisfaction to customers
and reduction of lead time are critical in the make-to-order manufacturing
system. It is difficult to schedule the production planning due to the
complexities of the shoes production processes. This study presents an
algorithm of the new planning system that satisfies the due-date and
considers specialties of shoes productions process. The ratio of the delivery
satisfaction has been improved from 54% to 84%, and the planning lead time
has been reduced from 14 days to 2 days. Moreover, we achieved several side
effects such as real time production planning and workload analysis,
information sharing over all departments, and improved flexibility in
receiving orders. The developed planning system with the algorithms has been
introduced in this paper, and we implement the system in the actual shoes
factory. |